Bragg Companies

Woods Cross, UT

Corporate Site


Springerville Generator Set

Bragg Crane & Rigging, in partnership with Heavy Transport hauled and installed a steam generator at the Springerville power plant. Using our prime mover and Goldhoffer THPH Heavy Transport hauled the turbine and generator to the building it would rest in to be lifted and set 60 feet above ground level. Bragg Crane & Rigging used their 850 ton gantry system and strand jack system to lift the units through and opening in the ceiling. When the unit reached the proper height the gantry walked the unit to be set in its place.

Call us:
(801) 272-6348
or email us at
and our representative will assist you.

2198 West 2425 South,
Woods Cross, UT 84087