I-15 Accelerated Bridge Construction

Heavy Transport and Bragg Crane & Rigging were contracted to complete Nevada Department of Transportation's Accelerated Bridge Construction. Using two SPMT's (Self Propelled Modular Transports) Heavy Transport and Bragg Crane & Rigging removed the existing rail bridge and replaced the it with a newer, stronger bridge using our own engineered "strong boxes" to set the bridge sections on our SPMT's. Heavy Transport and Bragg Crane & Rigging were alloted 24 hours to complete the job but only required 16 to complete it.

 

 

 